Critical path of a project is the shortest path on the network diagram:

2. 
In case of R&D type of projects which estimation technique is used?

3. 
Consider the following data for a project:

Activity                                  A   B  C   D   E     F           G       H    I     J     K

Activity Time (Days)           3   4   5   4    7       2           4       6    4     3     3

Immediate Predecessor      –    –    –    –    A    B,C,D    E,F    F    G    G    H


Draw the network diagram and calculate the critical path for this project

4. 
Which of the following is a schedule compression technique for projects:

5. 
Following are the precedence requirements, normal and crash activity times, and normal and crash costs for a project.

Activity                                         A         B         C            D             E         F              G            H             I

Immediate Predecessor            –          A          A            B             B,C      C             E,F         D,E         H,G

Normal Time (wks)                    4         3           2            5              1          3              4             4             6

Crash Time (wks)                       2          2           1            3              1           2             2              1             5

Normal cost ($)                      10000    6000    4000    14000    9000    7000     13000    11000    20000

Crash cost ($)                          11000    9000    6000    18000    9000    8000     25000   18000    29000


If you have to shorten the project by 3 weeks, what would the Final total cost be?