In the AOA network modeling, an event is represented by:

2. 
A dummy activity consumes time and resources

3. 
Consider A and B as the preceeding activities for C. The Earliest Finish time for A and B is 3 and 5 respectively.

What will be the Earliest start time for C?

4. 
If the latest occurance time of an event is 24th day, while the earliest occurance time of the event is 21st day, what will be the slack of this event?

5. 
Consider the following data for a project:

Activity                                         A     B    C      D    E       F      G      H    I        J

Activity Time (Days)                    2     4     5      2     1       8       3      5    4         7

Immediate Predecessor             –      A     A     B    B    B,C    D,E      F    F     G,H,I

Draw the network diagram and calculate the critical path for this project